What the projected total cost of the project will be at completion?

posted 10½months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 33, question 19
Earned Value Analysis

Which performance measurement tells us what the projected total cost of the project will be at completion?

A. ETC
B. CPI
C. SPI
D. EAC

george (10¼months ago):
The answer is D: EAC.

A: Estimate To Completion (how much we will spend more)
B: Cost Performance Index
C: Schedule Performance Index
D: Estimate At Completion