© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 32,question 17
Closing
The primary function of the Closing process is to:
A. Formalize lessons learned and distribute this information to project participants
B. Perform audits to verify the project results against the project requirements
C. Formalize project completion and disseminate this information to project participants
D. Perform post-implementation audits to document project successes and failures
george (2½years ago):
I think it's C. During Closing process we should formally close the project and distribute information about it among project stakeholders.