You are the project manager for Lucky Stars Candies. You’ve identified the deliverables and requirements and documented them where?

A. In the scope statement, which will be used as in input to the Scope Definition process
B. In the scope definition document, which is used as an input to the Scope Planning process
C. In the WBS, which is an output of the Scope Planning process
D. In the WBS, which is a tool and technique of the Scope Definition process