Which project-scheduling techniques allows for conditional and probabilistic treatment?

posted 10½months ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 31, question 13
CPM | GERT | PERT | Schedule | Scheduling Technique | Time Management

Which of the following project-scheduling techniques allows for conditional and probabilistic treatment?

A. GERT
B. CPM
C. PERT
D. CPM and PERT