What is true regarding Configuration management?

posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 31, question 12
Change Control | Configuration Management

All of the following are true regarding configuration management except:

A. Requires all acceptance decisions to be made through the CCB
B. Serves as a change control system
C. Describes the physical characteristics of the product of the project
D. Controls changes to the characteristics of an item

NH (11¾months ago):
C. Describing the physical characteristics of a products is not part of configuration management.

(c) 2009-2012 thePMP.com, rev.346, 0.36sec