You are a project manager who has recently held a project team kickoff meeting where all the team members were formally introduced to each other. Some of the team members know each other from other projects and have been working with you for the past 3 weeks during the Planning processes. Which of the following is true?
A. Team building begins once all the members of the team are identified and introduced to each other. This team is in the storming stage of Team Development.
B. Team building begins at the Planning process. This team is in the storming stage of Team Development.
C. Team building begins once all the members of the team are identified and introduced to each other. This team is in the forming stage of Team Development.
D. Team building begins at the Planning process. This team is in the forming stage of Team Development.