posted 2¼years ago by Natalie2000
© Copyright: Project Management Professional (PMP) Study Guide by Kim Heldman, Sybex Inc., Alameda, CA, USA, 2002, page 29,question 5
Scope Management
You’ve been assigned as a project manager on a research and development project for a new dental procedure. You’ve published the scope statement and are working on the scope management plan. What is the purpose of the scope management plan?
A. It describes and documents a scope baseline to help make future project decisions.
B. It decomposes project deliverables.
C. It describes how project scope changes will be incorporated into the project and how project scope will be managed.
D. It describes how cost and time estimates can be composed for project scope changes.
george (2¼years ago):
It's C - how project scope will be managed. Other options better describe other documents:
A: it's scope statement
B: it's WBS
D: it's change control rules or something similar