In which phase of a project would you estimate activity duration and resources?

posted 14months ago by pin
© Copyright: BestSampleQuestions.com
Time Management

In which phase of a project would you estimate activity duration and resources?

a. Initiating
b. Executing
c. Planning
d. Controlling

george (11months ago):
During planning phase, the answer is C. Activity duration and resources estimation processes are parts of Time Management process.

(c) 2009-2010 thePMP.com, rev.343, 0.24sec
PMP® and PMBOK® are registered trademarks of Project Management Institute, Inc.