Network Diagram | Time Management
What kind of a relationship is implied when completion of a successor is dependent on initiation of its predecessor?
a. finish-to-start (FS)
b. finish-to-finish (FF)
c. start-to-start (SS)
d. start-to-finish (SF)
george (10¾months ago):
It's a very rare type of dependency, and it's Finish-To-Start (FS), choice A