Cost Estimating | Cost Management | Earned Value Analysis
One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and:
a. divide it by the schedule performance index.
b. multiply it by the schedule performance index.
c. multiply it by the cost performance.
d. divide it by the cost performance index.