A project should be terminated for all of the following reasons except:
a. lack of team synergy.
b. the project no longer meets the company's objectives.
c. the resources are not available to complete project activities.
d. project funding has been significantly reduced.
george (2¼years ago):
The answer is A - project should NOT be terminated due to the lack of team synergy. We shall do something with the team, but NOT terminate the project.
Other options are good reasons for project termination.
mark94121 (2¼years ago): the answer was rejected by moderator
deewanand (2¼years ago):
b. the project no longer meets the company's objectives.