posted 9½months ago by Illia
© Copyright: Rita Mulcahy, PMP Exam Prep, Rita's Course in a Book for Passing the PMP Exam, Fifth Edition, RMC Publications Inc. (2005), page 81, question 10
Planning | Process | WBS
A project manager does not have much time to spend planning before the mandatory start date arrives. He therefore wants to move through planning as effectively as possible. Which of the following would you recommend?
A. Make sure you have a completed preliminary project scope statement and then start the WBS.
B. Create an activity list before creating a network diagram.
C. Document all the known risks before you document the high level assumptions.
D. Finalize the quality management plan before you determine quality metrics.
george (9½months ago):
I guess the right answer is: A. Scope is the most important component of the project success, and scope will impact all other components: activity list, risks, quality metrics.
webhead (8¾months ago): the answer was rejected by moderator