Scope Management | WBS
A Work Breakdown Structure (WBS) numbering system should allow project staff to:
a. identify the level at which individual WBS elements are found
b. identify configuration management milestones
c. estimate the costs of WBS elements
d. provide project justification
ksee00 (13months ago):
a. identify the level at which individual WBS elements are found