Time Management
Activity duration estimate inputs include all of the following except:
a. resource requirements
b. basis of estimates
c. activity lists
d. constraints
george (10¾months ago):
I think it's A, resource requirements is not an input to duration estimate. Duration and resource estimates are performed independently.