The _________ is a time-phased budget that will be used to measure and monitor cost performance in the project.

posted 14months ago by pin
© Copyright: BestSampleQuestions.com
Budget | Cost Baseline | Cost Management

The _________ is a time-phased budget that will be used to measure and monitor cost performance in the project.

a. work breakdown structure
b. project schedule
c. cost baseline
d. cost budget

george (10½months ago):
It is cost baseline, answer is C. Usually presented as S-curve it's a time-phases budget, used to track project performance.