Scope Management | Scope Verification
An example of scope verification is:
A. reviewing the performance of an installed software module
B. managing changes to the project schedule
C. decomposing the WBS to a work package level
D. performing a benefit/cost analysis to determine if we should proceed with the project
george (3½years ago):
I think it's A. When we review the performance of an installed module we verify whether produced deliverables (software module) comply to the scope (software non-functional requirements). Other options:
B: it's time management
C: it's scope definition, not verification
D: it's integration management