posted 15½months ago by Illia
© Copyright: Rita Mulcahy, PMP Exam Prep, Rita's Course in a Book for Passing the PMP Exam, Fifth Edition, RMC Publications Inc. (2005), page 291, question 13
Human Resource Management | Schedule
A project manager must publish a project schedule. Activities, start/end times and resources are identified. What should the project manager do NEXT?
A. Distribute the project schedule according to the communications management plan.
B. Confirm the availability of the resources.
C. Refine the project management plan to reflect more accurate costing information.
D. Publish a bar chart illustrating the timeline.
(c) 2009-2010 thePMP.com, rev.342, 0.22sec