Which process is applied to break down the project into smaller, more manageable elements?

posted 14months ago by pin
© Copyright: BestSampleQuestions.com
Scope Management

Which process is applied to break down the project into smaller, more manageable elements?

a. Scope Planning.
b. Activity Duration Estimating.
c. Scope Definition.
d. Scope Verification.

george (11months ago):
The answer is C. WBS is used to break down the project into smaller elements. And WBS is part of Scope Definition.