What is the relationship between project phases and the Project life cycle?

posted 2½years ago by pin
© Copyright: Oliver F. Lehmann PMP Self Test, oliverlehmann.com
Project Life Cycle | Project Phase | Time Management

Which of the following statements describes best the relationship between project phases and the Project life cycle?

A.The Project life cycle includes the time when the project is performed and the expected product lifespan after that.
B. In project management, the sequence of project phases and phase gates is often referred to as Project life cycle.
C. The Project life cycle is regarded as a sequence of project activities while phases are defined to control overlapping activities.
D. The Project life cycle describes how iterations of project management processes are used when a project schedule is developed.

priyasek (2¼years ago): the answer was rejected by moderator