What goes after risk response plan?

posted 16¼months ago by george
© Copyright: Rita Mulcahy, PMP Exam Prep, Rita's Course in a Book for Passing the PMP Exam, Fifth Edition, RMC Publications Inc. (2005), page 355, question 17
Risk Management

A project manager has just finished the risk response plan for a U.S. $387,000 engineering project. Which of the following should he probably do NEXT?

A. Determine the overall risk rating of the project
B. Begin to analyze the risks that show up in the project drawings
C. Add work packages to the project work breakdown structure
D. Hold a project risk reassessment

Illia (16months ago):
Right answer is - C.
A - Overall risk rating shall be determined at the qualitative risk analisys.
B - This work is performing during project execution.
D - This is what should be done right after risk response planning in risk process, but question is what should be done next (means in project planning)